Street Rehabilitation Project No. 2026-02

  • Project typePublic Works
  • Project status/phaseConstruction
  • Project schedule2026
  • Project areaHighway 65 East Service Drive, 63rd Avenue, 53rd Avenue, Skywood Lane, Lincoln Street, 52nd Avenue

The Street Rehabilitation Project No. ST2026-02 includes pavement rehabilitation improvements across approximately 1.46 miles of various segmented streets in three distinct project areas throughout the City. A map of project streets has been included below.

Project-Area-Map-Webpage.jpg

Current Project Updates

October 2, 2026

This week, the Contractor completed asphalt paving along Skywood Lane, 53rd Avenue, Lincoln Street, and 52nd Avenue.

Next week, the Contractor plans to install the final lift of asphalt pavement along 63rd Avenue.

Over the course of the coming weeks, the Contractor will be on site intermittently to perform minor work and address items missed during construction. During this time, project residents are encouraged to reach out to staff with any outstanding construction-related items.

For additional information, please see the official emailed notice.(PDF, 197KB)

 

Fill Out Project Survey

 

To sign up for project updates, enter your e-mail in the survey to be automatically signed up for project updates or email us at:

Web-StreetProjects@FridleyMN.gov

For the latest project information and to sign up for project notifications, please check the project webpage. If you have any questions or comments, please call us at 763-572-3554 or email web-streetprojects@fridleymn.gov.

 

Project Public Meetings

 

Past Project Updates

September 25, 2026

This week, the Contractor adjusted existing surface utilities within the roadway on previously paved streets and milled the existing pavement on Skywood Lane, 53rd Avenue, Lincoln Street, and 52nd Avenue.

Next week, the Contractor plans to install asphalt pavement along 63rd Avenue, Skywood Lane, 53rd Avenue, Lincoln Street, and 52nd Avenue. 

For additional information, including updates regarding paving and street parking, please see the official emailed notice.(PDF, 196KB)

September 17, 2026

This week, the Contractor began adjustment of existing surface utilities within the roadway. Next week, the Contractor will continue utility adjustments and is anticipated to mill the existing pavement along Skywood Lane, 53rd Avenue, Lincoln Street and 52nd Avenue in preparation for paving.

For additional information on upcoming construction activity, please see the official emailed notice.(PDF, 7MB)

 

September 11, 2026

This week, the Contractor installed the first lift of asphalt along Highway 65 East Service Road and 63rd Avenue.

Next week, the Contractor plans to adjust existing surface utilities within the roadway on streets with asphalt pavement in place. The Contractor will also be repairing a sewer main on Highway 65 East Service Road.

For additional information, please see the official emailed notice.(PDF, 197KB)

 

September 4, 2026

This week, the Contractor successfully reclaimed the existing pavement, adjusted surface utilities, and graded the roadway base along the Highway 65 East Service Road and 63rd Avenue. This work has finalized the stabilization of the road base in preparation for upcoming paving. 

Next week, the Contractor will install the first lift of asphalt pavement along Highway 65 East Service Road and 63rd Avenue, with driveway access and local traffic flow being maintained throughout. 

For additional project information, including the street parking notice, please see the official emailed notice.(PDF, 197KB)

August 31, 2026

The City’s Contractor, Park Construction Company, is anticipated to start construction activities beginning Tuesday, September 1st. The Contractor is scheduled to reclaim the existing pavement along Highway 65 East Service Road and 63rd Avenue on Tuesday.

Following the pavement reclamation, the roadway on both Highway 65 East Service Road and 63rd Avenue will be a gravel driving surface. Driveway access and local traffic flow will be maintained throughout the project.

For additional information, as well as how to sign up to receive weekly emailed updates, please see the official emailed notice(PDF, 431KB). 

October 13, 2025

On October 8th, an Open House was held at City Hall. Project staff had a chance to meet with residents in the project area and answer questions regarding the upcoming construction. Staff then shared a presentation with those who attended which highlighted the anticipated schedule, what to expect during construction, and how to navigate the assessment process. If you were unable to attend the Open House, the presentation can still be viewed here(PDF, 6MB). 

Fill Out Project Survey

 

September 24, 2025

Invitations were recently mailed to residents and property owners within the project (ST2026-02) area. The mailing announced an upcoming open house on Wednesday, October 8, 2025, during which a presentation will be given on the project, followed by an opportunity for questions.