Street Rehabilitation Project ST2026-01

  • Project typePublic Works
  • Project status/phasePlanning Phase
  • Project scheduleConstruction Summer 2026
  • Project areaMelody Manor Neighborhood

The Street Rehabilitation Project ST2026-01 is scheduled to begin construction in 2026 and will include the rehabilitation of several asphalt street segments, watermain replacement in select areas, and minor utility repairs in the Melody Manor neighborhood.

Project Overview

The video below is a recording from the second 2026 Street Rehabilitation Project Open House. Staff goes over the scope of work being performed, what to expect during construction, and other additional information pertaining to the project. 

Fill Out Project Survey  

Current Project Updates

October 24, 2025

The feasibility study for the 2026 Street Rehabilitation Project was approved by City Council on October 13, 2025. Hearing notices were mailed today, and property owners should expect to receive them next week. Each notice includes hearing details and an individual preliminary assessment estimate for each affected property. The City Council has scheduled a public hearing which will take place on November 10, 2025 during the Council Meeting at Fridley Civic Campus. Residents in the 2026 project area are encouraged to attend as preliminary assessments will be discussed. For further information regarding this part of the process, please see the official emailed notice(PDF, 161KB).

 

If you would like to be added to our project update group, please email web-StreetProjects@fridleymn.gov.

Previous Project Updates

October 8, 2025

On October 2nd, a second Open House was held by project staff. A Q&A session was held before a presentation was given detailing the project specifications, anticipated timeline for the project, as well as information on the assessment process. If you were unable to attend the Open House, the presentation can be viewed here(PDF, 3MB).

The project map below was included with the mailing and identifies both 2026 and 2027 construction areas. 

Updated-Project-Map.jpg

 

 

September 18, 2025

Invitations were recently mailed to residents and property owners within the 2026 Street Rehabilitation Project (ST2026-01) area. The mailing announced an upcoming open house on Thursday, October 2, 2025, during which a presentation will be given on the 2026 project, followed by an opportunity for questions.

June 12, 2025

Residents and property owners in the area of the proposed street project received an invitation in the mail for the Street Rehabilitation Project ST2026-01 Open House. Within that invitation, there is a survey mentioned where we're asking for resident feedback on some important components to the project. To complete yours, please visit the electronic survey form to submit your input. 

project-map.jpg

 

Project Public Meetings